How Export → Sprint report · PDF renders. A paginated, print-ready document — cover + executive summary, the three agile charts, scope-change log and the shipped-ticket ledger. Same chart language and tokens as the live Reports screen, laid out for letter-size paper.
The team committed 34 pt across 18 tickets and has completed 21 pt (62%) through day 7. Burndown sits 2 pt behind the ideal line after a mid-sprint scope addition on the Acme record migration. At the current pace the sprint is projected to finish roughly one day late; descoping the SSO test to Sprint 25 partly offset the added work. Velocity remains in band at an average of 23 pt over the trailing five sprints.
| Ticket | Title | Owner | Pts |
|---|
How Export → Charts · PNG renders. A single flat image at 1200 × 675 — the three charts on one branded board, sized to drop straight into Slack, a status update or a deck. No tables or prose, just the visuals.